How to track renovation expenses, from the first payment to the last
Tracking a renovation takes three numbers, not one: what you planned, what you have agreed to, and what you have paid. Log the amount the day you agree, log each payment the day it goes out, and add it up by room once a week. The surprise comes from watching only what has been paid.
“Log the committed number the day you agree to it and receipts become reconciliation instead of discovery.”
Real forum reply, Jul 2026: BiggerPockets
That advice came from someone who runs big jobs, in an investors' forum. It fits a condo kitchen just as well: the number goes into the notebook on the day of the handshake, and the receipt only confirms it later.
The three numbers
- Planned: what you mean to spend, by room. A guess is fine. A guess written down is already a yardstick.
- Agreed: what you have settled with each contractor and store, plus change orders. Money that has not left yet, but already has an owner.
- Paid: what actually went out, with a receipt.
"How much have we spent?" is paid. "How much is left?" is agreed minus paid. "Will the money last?" is agreed against planned. If you only watch paid, you find out you are over budget when the money runs out.
Step by step
- Before you start: list the rooms and write a planned amount for each.
- At every deal: write who, what, how much, in how many installments, and the date. Text the summary to the contractor and get an "ok" back.
- At every "that's extra": log it as a change order, with an amount and a date, before the work starts.
- At every payment: log it the same day and keep the receipt with it. Cash too.
- Every Sunday: look at the total by room and at next week's payments.
What slips through most
- Cash to a helper and for deliveries.
- Small supply runs, three times a week.
- The change order agreed out loud, on site, with no number.
- The dumpster, which is never just one.
When a room goes over
Going over is not a math mistake. It is information. See what is still unbought in that room and what you can swap. A kitchen that is 2,300 over still has finishes waiting to be picked.
Where Caderno da Obra comes in
The app keeps the three numbers on the first screen: spent so far, out of how much planned, and how much is still to pay on what you agreed. A change order joins the plan on the day you log it. Each room has its own bar, and when it goes over, the number changes color. No alarm.
Read next
- A free renovation budget spreadsheet, and how to keep it going to the endDownload a free renovation budget spreadsheet template with the columns that matter. And see why most of them stall in week three.
- "That's extra": how to agree on and log a change order without a fightChange orders are the top source of arguments and budget overruns in a renovation. A four-item rule to settle one before the work starts.
- Why log the amount the day you agree, not the day you pay?Logging the committed number the day you agree turns receipts into a check, not a discovery. The method in three steps.