"That's extra": how to agree on and log a change order without a fight
A change order is any work that was not in the original agreement. The rule that prevents the fight has four items: what it is, what it costs, the date, and the contractor's "ok" in writing, all before the work starts. A change order logged after the work is done has already become an argument.
“[…] Antes, muitas informações ficavam perdidas no WhatsApp. […]”
Our translation: “[…] Before, a lot of information got lost in WhatsApp. […]”Real review, 5 of 5 stars, Oct 2026, of another app: Obra Controle, App Store (Brasil)
The scene is always similar. Saturday, on site, the contractor says the bathroom tile is extra. You are sure it was included. The proof is in one of forty voice notes. Nobody is lying: each of you remembers it differently.
Why change orders weigh so much
- They start out loud, mid-job, with no fixed number.
- Small one by one, large in total. Five change orders of 400 are 2,000 that were never in the plan.
- They only show up at the end, with the final installment, when money is tightest.
The four-item rule
- What: "a niche in the hall bathroom shower".
- How much: a number, not "we'll see later".
- When: the date you agreed.
- The ok: one message with the three items above, and the contractor replies "ok".
It takes two minutes and protects both of you. An honest contractor, which is most of them, prefers it too: nobody wants to do the work and argue about the price afterward.
What about one that is already done?
Talk it through with the original agreement in hand. If the work was described there, it is not a change order. If it was not, it is, and what is left is to settle on a fair amount and write it down, so the next one does not repeat the story.
Count it the day you agree
A change order joins the cost of the renovation on the day it is agreed, not the day it is paid. That way the planned total tells the truth today.
Where Caderno da Obra comes in
In the app, a change order is a kind of agreement, linked to the original one. It joins the plan the day you log it, and the first screen says how much of the plan is change orders. The agreement comes out as an image card you can send to the contractor, with the date on it. It is not a contract. It is the agreement with a date, so you both remember it the same way.
Read next
- How do I find what I agreed with my contractor in a long chat thread?Renovation agreements get buried under voice notes and photos in a chat app. How to recover what was said and how to write it down from now on.
- Fixed bid or day rate: how to set up contractor payments and know what is leftThe difference between a flat price and a day rate, how to tie contractor payments to finished stages, and a calculator for what is left to pay.
- How do I avoid getting ripped off by a contractor?Most renovation fights start with an undated agreement, not with bad faith. What to write down to protect yourself without treating anyone as a suspect.